Water supply Nymburk-Chotuc
Czech Republic Water supply Nymburk-Chotuc Stav tendru: vypsaný tendr Banka:
Evropská investiční banka Klíčová slova: rozvod vody Popis: EIB - Water supply
Nymburk-Chotuc (CZ-Nymburk) 2002/S 204-160561 Vodovody a kanalizace Nymburk
a.s., Bobnická 712, 288 21 Nymburk represented by VIS spol. s.r.o., Hradec
Králové Na Streziné 1079, 500 03 Hradec Králové in accordance with Public Tender
Act No. 199/94 Coll., in its full version (hereinafter only \"the Act\") public
tender (hereinafter only \"PT\") for delivery of a construction \"Water supply
Nymburk - Chotuc\" 1. Specification of the public tender The subject of the
public tender is the execution and supplying of all works and the delivery of
all tasks necessary for total completion of the \"Group water mains Nymburk -
Chotuc\" construction and for their successful putting into trial operation. The
construction contains: - construction objects SO 01.1 feeder I (Nymburk -
Chotuc) SO 01.2 feeder IIa (Nymburk - Krchleby) feeder IIb (Chotuc - Jikev) ATS
Vsechlapsky vrch SO 01.3 feeder III (Chotuc - Rozdalovice) ATS Rozdalovice SO
01.4 feeder IV (Sv. Jan - Mcely) Filling station - Sovenice SO 01.7 feeder VIIa
(Chotuc - Vestec) SO 01.8 feeder VIII (Jikev - Loucen) Filling station - Jikev
SO 02.3 feeders Jikev SO 02.5 feeders Oskorinek SO 02.8 feeders Knnec SO 02.11
feeders Rozdalovice SO 03.1 water reservoir Chotuc 2Ă—500 m3 SO 03.2 access
communication to the water reservoir SO 03.3 water reservoir waste SO 04 NN
connections - operation sets PS 01 Support of pumping at UV Podecely PS 02 CS ÚV
Nymburk (Babin) PS 03 VDJ Chotuc PS 04 CS, ATS Rozdalovice, Sovenice, Jikev,
Vsechlapy PS 05 Electric part It is ca 70.504 km of water mains DN 80 - 300, 3
pcs of ATS and a filling station and a water reservoir Chotuc in total. Any
activities of the supplier, detail and shop drawings documentation, as is
documentation and geodetic survey are a part of the subject of public order
accomplishment. 2. Time and place of the performance of the public tender The
principal requires that the time of performance be in the following terms: -
construction commencing: within 1 month from the conclusion of the Contract of
Work conclusion with the chosen supplier; - construction finishing: within 25
months from the construction commencing - by 12/2004 at the latest. The tenderer
may offer shorter time of construction. The principal reserves the right to
change running terms and termination date of public tender accomplishment in
accordance with draw of the financial means from the state budget. The place of
public tender performance is the area of Nymburk, Chotuc, Krchleby, Jikev,
Rozdalovice, Mcely, Sovenice, Vestec, Loucen, Krinec and Oskorinek. The detailed
description of the public tender performance is mentioned in the tender
documentation. publikováno: 21.10.2002
Czech Republic
Water supply Nymburk-Chotuc
Stav tendru: vypsaný tendr
Banka: Evropská investiční banka
Klíčová slova: rozvod vody
Popis:
EIB - Water supply Nymburk-Chotuc (CZ-Nymburk)
2002/S 204-160561
Vodovody a kanalizace Nymburk a.s., Bobnická 712, 288 21 Nymburk
represented by VIS spol. s.r.o., Hradec Králové
Na Streziné 1079, 500 03 Hradec Králové
in accordance with Public Tender Act No. 199/94 Coll., in its full version
(hereinafter only \"the Act\")
public tender
(hereinafter only \"PT\")
for delivery of a construction
\"Water supply Nymburk - Chotuc\"
1.
Specification of the public tender The subject of the public tender is the execution and supplying of all works and the delivery of
all tasks necessary for total completion of the \"Group water mains Nymburk - Chotuc\" construction and for their successful
putting into trial operation.
The construction contains:
- construction objects
SO 01.1 feeder I (Nymburk - Chotuc)
SO 01.2 feeder IIa (Nymburk - Krchleby)
feeder IIb (Chotuc - Jikev)
ATS Vsechlapsky vrch
SO 01.3 feeder III (Chotuc - Rozdalovice)
ATS Rozdalovice
SO 01.4 feeder IV (Sv. Jan - Mcely)
Filling station - Sovenice
SO 01.7 feeder VIIa (Chotuc - Vestec)
SO 01.8 feeder VIII (Jikev - Loucen)
Filling station - Jikev
SO 02.3 feeders Jikev
SO 02.5 feeders Oskorinek
SO 02.8 feeders Knnec
SO 02.11 feeders Rozdalovice
SO 03.1 water reservoir Chotuc 2Ă—500 m3
SO 03.2 access communication to the water reservoir
SO 03.3 water reservoir waste
SO 04 NN connections
- operation sets
PS 01 Support of pumping at UV Podecely
PS 02 CS ÚV Nymburk (Babin)
PS 03 VDJ Chotuc
PS 04 CS, ATS Rozdalovice, Sovenice, Jikev, Vsechlapy
PS 05 Electric part
It is ca 70.504 km of water mains DN 80 - 300, 3 pcs of ATS and a filling station and a water reservoir Chotuc in total.
Any activities of the supplier, detail and shop drawings documentation, as is documentation and geodetic survey are a part of
the subject of public order accomplishment.
2.
Time and place of the performance of the public tender The principal requires that the time of performance be in the following
terms:
- construction commencing: within 1 month from the conclusion of the Contract of Work conclusion with the chosen supplier;
- construction finishing: within 25 months from the construction commencing - by 12/2004 at the latest.
The tenderer may offer shorter time of construction. The principal reserves the right to change running terms and termination
date of public tender accomplishment in accordance with draw of the financial means from the state budget.
The place of public tender performance is the area of Nymburk, Chotuc, Krchleby, Jikev, Rozdalovice, Mcely, Sovenice, Vestec,
Loucen, Krinec and Oskorinek. The detailed description of the public tender performance is mentioned in the tender documentation.
publikováno: 21.10.2002